Site Outline 111 acres
Water
Wastewater
Rail
Electric
Telecommunications
top layer
Electric:
12.47kV 3-phase distribution circuit with 2.5MW capacity (0.4 mile extension required to reach site, 6 month estimated completion)
power lines
Existing
proposed power lines
Proposed
Duke Energy
Water:
8" line 55 PSI
water lines
Existing
proposed water lines
Planned 12” line, completion by 2021/2022
City of Zephyrhills
Wastewater:
6” line (line upgrade possible approximately 6 months)
wastewater lines
City of Zephyrhills
Telecommunications:
Fiber available
Telecommunication lines
Frontier
Natural Gas:
4” main extension to site approximately 3 months

TECO Peoples Gas